In the general case, both the priority of the construction of objects, and the technological sequence of work execution allow either sequential, or parallel, or continuous (combined) construction, which may also include their rational combinations.
The considered groups of construction methods are relatively independent with each other, which implies the possibility of their joint use. For example, a fairly large-scale construction can be divided into nodes and blocks, and nodal and complete-block methods can be applied to it. and, in view of its remoteness from the location of the construction organization, work can be carried out by the expeditionary rotational system. From the position of the same combination of construction work in time, all construction and installation processes can be organized by one of the flow methods. Thus, with this approach, the principle of a rational combination of various methods and methods of organizing construction is implemented.