Consists of 3 stages:
1. Organizational measures (carried out without a working class)
2. Works of the preparatory period
a. offsite
b. onsite
3. Preparatory work (performed before the start of each work)
Organizational events
The customer must obtain a building permit and pass it on to the contractor. The customer receives permission from the local government administration, for which he must submit, together with the application, the land title documents, the land development plan of the land plot (cadastral plan), all materials contained in the design and estimate documentation, a positive conclusion of the state examination (if conducted), reconstruction consent of all owners of the object.
Permissions for objects are not required:
- construction of a garage on a land plot provided to an individual, or a land plot provided for gardening or dacha farming
- construction, reconstruction of objects that are not objects of capital. construction (kiosks, awnings)
- buildings and structures of auxiliary use
The building permit is issued for the period stipulated by the PIC. Permission for individual housing construction for 10 years. The validity period may be extended by the authority that issued the permit, on an application submitted no later than 60 days before the expiration date. May be refused if construction is not commenced before the expiration date.
For objects controlled by GOSSTROYNADZOR, it should show the full address of the construction, who is the customer, engineer for technical supervision, data, contact numbers, who will carry out the construction, data of the foreman, contact numbers, the same for author's supervision, extracts from orders on responsible persons magazine production work.
Transfer of the site for the construction of the contractor
When transferring the site, the customer must:
1. to transfer the existing communications to be transferred (demolished)
2. to vacate the site from existing structures to be demolished (buy real estate, relocate citizens)
3. bring the necessary engineering communications to the site, provide tie-in conditions to the existing communications
4. in the forested area to make a forest cover
5. creation of a reference geodetic network.
The contracting construction organization is developing an outage. Based on the developed PPR, the contracting construction company concludes contracts for the supply of structures, materials, decides on the acquisition of additional equipment and equipment. At the same time, the customer, on the basis of a custom specification of equipment, concludes contracts for the supply of technological and other types of equipment.
The contractor should consider the compliance of its power to the task.
Works of the preparatory period
Off site
Creation of off-site infrastructure:
- construction of the town of builders
- construction of the necessary base of the construction organization
- concrete-mixing units for the whole construction site
- workshops
- UPTK base (management of production and technological equipment)
- external communications to the site
Onsite
The site-wide planning, cutting of the soil layer of the soil, laying of permanent and temporary on-site communications, networks of energy, water, heat, gas supply, construction of roads and railways are carried out. At the same time, on-site warehouses are designated, a campsite is being created.
Preparation of construction organizations for the autumn-winter and spring and flood period
For the autumn-winter
1. prepare specials. clothes
2. repair cabins
3. stock up on greenhouses
4. convert the equipment to winter lubrication, prepare antifreeze
5. mark in open warehouses where what lies
6. before the onset of frost do drainage channels
By spring and flood
1. provide water flow
2. to strengthen the masonry structures nazamorazhivanie